IZMIR–ISTANBUL BRIDGE AND ROAD-WAY PROJECT

North Anchoring Construction: A total of 44,000 m³ of concrete; 20,680 m² formwork; 6,500 tons of iron work will be carried out at foundation and abutments.
Progress: 48.24% at North Anchorage Block; 36.14% at Triangular Pier.
Sidespan Pier works are awaiting the site delivery by employer.